Project overview

Auckland Transport, in partnership with the Rodney Local Board, is implementing a new a one-way bus service. The new bus route, 999, will run one way around Warkworth in a clockwise direction approximately every 30 minutes.

Route 999 will enhance access to public transport for local commuters along Percy Street, Lilburn Street, Pulham Road, Woodcocks Road, Mansel Drive and Hill Street. These bus stops aim to provide residents with convenient access to the bus route, improving public transport connectivity within the community and safety for buses, bus users, pedestrians and other road users.

To allow buses to pull into and out of the proposed bus stops safely, some parking will be removed as part of this proposal. We understand that the removal of parking can be inconvenient, so we’ve minimised it as much as possible.

Aerial photo showing the route of the new 999 bus service in Warkworth

Project details

This project includes the installation of 6 new bus stops along the new route. The locations of these bus stops are:

1. 21 Percy Street (outside medical centres)

Install new bus stop with road marking and signage

2. 25 Lilburn Street

  • Install new bus stop with road marking and signage
  • Replace existing footpath with wider, extended concrete hardstand (concrete pad)
  • Replace drop kerb with new kerbing in line with TDM standards

3. Opposite 7 Pulham Road

Install new bus stop with road marking and signage

4. 15 Woodcocks Road (outside Mahurangi College)

Install new bus stop with road marking and signage

5. Opposite 20 Mansel Drive (outside Summerset Falls Retirement Village)

  • Install new bus stop with road marking and signage
  • Install new hardstand (concrete pad)
  • Install yellow tactile pavers to help guide blind and low-vision users

6. 62 Hill Street

  • Install new bus stop with road marking and signage
  • Install concrete hardstand (concrete pad) in line with TDM standards

Download project drawings (PDF 8.6MB)

What happens next

Construction is expected to begin in June 2024. We will notify nearby properties a week before construction works start.